What It Looks Like Now

Current Construction Progress Video | September 27th - October 18th

What's Coming In The Future


Construction Progress Video Archive
September 1st - September 19th
August 1st - August 15th
July 17th - July 27th
June 19th - July 12th
May 25th - June 14th
May 17th - May 24th
    Construction is scheduled to be complete by January 2018

  • Classes are being held in other Club Houses and in the Temporary Buildings located at the Del Valle parking lot: check here for available classes

  • CONSTRUCTION PROGRESS UPDATE - AS OF THE WEEK OF OCTOBER 23

    Exterior Highlights:
  • Roofing over the Fitness Equipment and the new High Roof is completed.
  • New concrete sidewalks in front of the building are now complete, with decorative pavers to be installed in November.
  • Large window frames will be installed at the end of October and should be completed by mid-November.
  • Exterior plaster work is continuing and all scaffolding should be removed by mid-November.

  • Interior Highlights:
  • Drywall is being completed throughout the interior.
  • Electrical and cabling for video screens throughout the facility and at new exercise equipment is being installed.
  • Locker Rooms are almost complete, with shower and toilet partitions being installed within the next few weeks.
  • Fitness equipment has been ordered and is set for delivery in early December.
  • Furniture has been ordered and is set for delivery by middle December.
  • The temporary Fitness Center at the modular buildings in the parking lot is currently expected to close in mid-December.
  • The fully renovated center is expected to open to residents for initial tours and orientations in early January 2018.