What It Looks Like Now

Current Construction Progress Video | September 1st - September 19th

What's Coming In The Future


Construction Progress Video Archive
August 1st - August 15th
July 17th - July 27th
June 19th - July 12th
May 25th - June 14th
May 17th - May 24th

    Construction is scheduled to be complete by January 2018
  • Classes are being held in other Club Houses and in the Temporary Buildings located at the Del Valle parking lot: check here for available classes

  • Exterior Highlights:
  • Roofing over the Fitness Equipment and the new High Roof is almost completed.
  • A crane to lift a large air conditioning unit will partially block Comstock Drive (vehicles will still be able to pass).
  • This work is scheduled for the end of September.
  • Large storefront window frames will begin installation around the beginning of October and should be complete in about two weeks.
  • Exterior plaster is also scheduled to start at the beginning of October.

  • Interior Highlights:
  • Walls are being completed, so rooms are now taking shape.
  • Ceiling installations are starting the week of September 25, with completion in approximately 2 weeks.
  • Locker Rooms are being tiled, with shower partitions, dressing areas and plumbing fixtures being finished in approximately 4 to 6 weeks.
  • Interior finishes such as painting and flooring will be installed during the month of October and early November.
  • Fitness equipment has been ordered and is set for delivery in early December.
  • The temporary Fitness Center at the modular buildings in the parking lot are currently expected to close in mid-December.
  • The fully renovated center is expected to open to residents for initial tours and orientations in early January 2018.